Szczegóły

Tytuł artykułu

Identification and prioritization of factors influencing the increase in construction costs of building investments using factor analysis

Tytuł czasopisma

Archives of Civil Engineering

Rocznik

2021

Wolumin

vol. 67

Numer

No 3

Afiliacje

Seyedebrahimi, Seyedkazem : Department of Civil Engineering, Yazd Branch, Islamic Azad University, Yazd , Iran ; Mirjalili, Alireza : Department of Civil Engineering, Yazd Branch, Islamic Azad University, Yazd , Iran ; Sadeghian, Abolfazl : Department of Management, Yazd Branch, Islamic Azad University, Yazd, Iran

Autorzy

Słowa kluczowe

cost ; construction projects ; hierarchical analysis ; Yazd city

Wydział PAN

Nauki Techniczne

Zakres

705-722

Wydawca

WARSAW UNIVERSITY OF TECHNOLOGY FACULTY OF CIVIL ENGINEERING and COMMITTEE FOR CIVIL ENGINEERING POLISH ACADEMY OF SCIENCES

Bibliografia


[1] M. Aslam, E. Edmund Baffoe-Twum, F. Saleem, “Design Changes in Construction Projects Causes and Impact on the Cost”, Civil Engineering Journal, 5(7), pp. 1647–1655, 2019. https://doi.org/10.28991/cej-2019-03091360
[2] U. Haider, U. Khan, A. Nazir, M. Humayon, “Cost Comparison of a Building Project by Manual and BIM”, Civil Engineering Journal, 6(1), pp. 34-49, 2020. https://doi.org/10.28991/cej-2020-03091451.
[3] K. Ernest, A.K. Adjei-Kumi Theophilus, B. Edward, “Exploring cost planning practices by Ghanaian construction professionals”, Int. J. Project Organisation and Management, 9(1), pp. 83–93, 2017. https://doi.org/10.1504/IJPOM.2017.083112
[4] N. Ramlee, N. J. Tammy, R. Mohd Noor, R. N. H. Ainun Musir, A., Abdul Karim, N., H. B. Chan, , S. R. Mohd Nasir, “Critical success factors for construction project”, AIP Conference Proceedings, 1774, 030011, 2016. https://doi.org/10.1063/1.4965067
[5] T. A. Ghuzdewan, B. Petra, K. Narindr, “Project Cost Estimation Based on Standard Price of Goods and Services”, (SHBJ) MATEC Web of Conferences, 2018, p. 159, https://doi.org/10.1051/matecconf/201815901012
[6] T. Al Amria, M. Marey-Pérezb, “Towards a sustainable construction industry: Delays and cost overrun causes in construction projects of Oman”, Journal of Project Management, Journal of Project Management, 5, pp. 87–102, 2020. https://doi.org/10.5267/j.jpm.2020.1.001
[7] S. Štuheca, G. Verhoevenb, I. Štuhecc, “Modelling building costs from 3d building models estimating the construction effort from image-based surface models of dry-stone shepherd shelters (kras, slovenia)”, The International Archives of the Photogrammetry, Remote Sensing and Spatial Information Sciences, Volume XLII-2/W9, https://doi.org/10.5194/isprs-archives-XLII-2-W9-691-2019.
[8] D. Aničić1, J. Aničić, “Cost management concept and project evaluation methods, Journal of Process Management New Technologies”, International, 7(2), pp. 54–59, 2019. https://doi.org/10.5937/jouproman7-21143.
[9] A. Q. Memon, A. H. Memon, M. A. Soomro, I. A. Rahman, “Common factors affecting time and cost performance of construction projects in Pakistan”, Pakistan Journal of Science, 71, pp. 64–68, 2019. http://apicee.org/Files/Paper1%20(11).pdf
[10] B. Boahene Akomah, W. Justice, M. Zakari, S. Kottey, “Cost impacts of variations on building construction projects”, MOJ Civil Eng, 4(5), pp. 386‒392, 2018. https://doi.org/10.15406/mojce.2018.04.00133.
[11] A. Pirasteh, “Studying factors affecting the increase in delays and costs of construction projects”, In: The second conference on civil engineering, architecture and urban planning of the Islamic World, Tabriz, 2018. https://civilica.com/doc/1021202/
[12] I. Gurkhani, M. Mohammadi, A. Sabet, “Identifying the effective factors on the occurrence of delays and cost increases in case study of Mehr Housing projects”, The First national conference on management, ethics and business, Shiraz, 2019. https://www.civilica.com/Paper-MEBCONF01-MEBCONF01_164.html
[13] M. Ahmadvand,H. Eghbali, N. Habibi Lasibi, “Presenting a model for evaluating the factors causing delays and increasing costs in construction projects”, Sixth National Conference on Applied Research in Civil Engineering, Architecture and Urban Management, Tehran, 2019. https://www.civilica.com/Paper-CEUCONF06-CEUCONF06_0086.html
[14] A. Ebrahimi Chamani, N. Ramezanpour, V. Azizifar, “Investigating the most important causes of delays and increased costs in road construction projects Case study: Mazandaran province road construction projects”, In: Fifth International Conference on Modern Research in Civil Engineering, Architecture, Urban Management and Environment, Karaj, 2019. https://civilica.com/doc/1000494/
[15] M. Hejazi, R. Norouzpour, “The role of project integration management in reducing construction project costs”, In: 7th national conference on accounting and management Applications, Tehran, Asia Golden Communication Group, 2015. https://civilica.com/doc/807502/
[16] M. A. Rasouli,T. Pourrostam, J. Majrouhi, “Simultaneous study of factors affecting time delays and cost increases in iranian hospital projects”, In: The first international conference on civil engineering, architecture and sustainable green city, Hamedan, 2017. https://civilica.com/doc/673678/
[17] M. Khalilzadeh, R. Mohammadi, “Factors affecting increasing the cost of construction projects in construction projects (Qazvin City)”, In: 12th international conference on project management, Tehran, 2016. https://civilica.com/doc/575121/
[18] T. L. Saaty, “Relative Measurement and its Generalization in Decision Making: Why Pairwise Comparisons are Central in Mathematics for the Measurement of Intangible Factors – The Analytic Hierarchy/Network Process”, Madrid: Review of the Royal Spanish Academy of Sciences, 2008, Series A, Mathematics. https://doi.org/10.1007/BF03191825
[19] O. Moselhi, N. Roofigari-Esfahan, “Compression of project schedules using the analytical hierarchy process.” J. Multi-Criteria Decis Anal 2012; 19: pp. 67–78, 2012. https://doi.org/10.1002/mcda.490
[20] A. Ishizaka, A. Labib, “Review of the main developments in the analytic hierarchy process”, Expert Syst. Appl., 38: pp. 14336–14345, 2011. http://dx.doi.org/10.1016/j.eswa.2011.04.143
[21] S. Kim, J. Lawson, Y. Lim, “The matrix geometric mean of parameterized, weighted arithmetic and harmonic means." Linear Algebra Appl., 435: pp. 2114–2131, 2011. https://doi.org/10.1016/j.laa.2011.04.010
[22] F.H. Lotfi, R. Fallahnejad, “Imprecise Shannon's entropy and multi attribute de-cision making”, Entropy ,12: pp. 53–62, 2010. https://doi.org/10.3390/e12010053
[23] S. Monghasemi, M.R. Nikoo, M.A. Khaksar Fasaee, J. Adamowski, “A novel multicriteria decision making model for optimizing time–cost–quality trade-off problems in construction projects”, Expert Syst. Appl., 42: pp. 3089–3104, 2015, https://doi.org/10.1016/j.eswa.2014.11.032.
[24] C. Cole, “Calculating the information content of an information process for adomain expert using Shannon’s mathematical theory of communication: Apreliminary analysis”, Inform Process Manag.; 33: pp. 715–726, 1997. https://doi.org/10.1016/S0306-4573(97)00038-1.
[25] T. Cunningham, “Cost Control during the Pre-Contract Stage of a Building Project An Introduction”, Report prepared for Dublin Institute of Technology, 2015. https://doi.org/10.21427/83w4-r689.

Data

2021.09.08

Typ

Article

Identyfikator

DOI: 10.24425/ace.2021.138079 ; e-ISSN 2300-3103
×